Purification Workshop Construction Process Flow :
Step 1: Floor polishing, primer for epoxy resin floor paint.
Step 2: Purification air conditioning and air supply pipeline installation.
Step 3: Installation of color steel plate partition wall.
Step 4: Purification equipment installation (air shower room,transfer window, etc.)
Step 5: Installation of color steel plate suspended ceiling.
Step 6: Door and window production and installation.
Step 7: Install air supply and return louvers.
Step 8: Install purification lamps.
Step 9: Tearing film and applying sealant.
Step 10: Topcoat for epoxy resin floor paint.
Step 11: Power on testing air conditioning, air supply system,purification equipment, lighting, etc.
Step 12: Completion acceptance and put into use.